September 21, 2023 — East Taggart Street has been closed to traffic since the Norfolk Southern train derailment in February. Currently, traffic on the closed portion of East Taggart Street—from east of North Pleasant Drive to the Ohio-Pennsylvania border—has consisted of an average of 75 to 100 trucks per day. These trucks transport waste, equipment, and materials in and out of the cleanup work areas. Because of the risks associated with that much heavy traffic—and to maintain the safety of residents of the Village and workers—the Unified Command leading the ongoing emergency response made the decision to keep East Taggart Street closed.

Now, as the cleanup work has progressed, the Unified Command has determined that East
Taggart Street can be safely opened in the overnight hours. This initial reopening will still
include the presence of safety signs, lights, flagging personnel, site security, access controls and associated equipment, with continued air monitoring of the project for environmental safety.

Although there are no anticipated health risks along East Taggart Street associated with project activities, the potential for cleanup-related odors may exist. As work proceeds, to ensure worker and community safety, the Unified Command will continue to evaluate site conditions for health and safety considerations. While traffic will be able to proceed through the work areas along East Taggart Street, access into active work areas will remain restricted to ensure public safety.

The Unified Command has established the following implementation schedule:

Phase I (Beginning on Monday, September 25)
Taggart Street will remain closed during daytime operations, from 5:30 a.m. to 7:30 p.m.
Overnight, East Taggart Street will be opened in both directions for all traffic to pass
through the worksite. Safety controls will remain, including: signage, reduced speed,
flaggers.

Phase II (Anticipated to begin on Monday, October 23)
Following the conclusion of major excavation and soil removal activities, traffic on East
Taggart Street will reopen in both directions all day. Periodic traffic stoppage—of up to
15 minutes or more—should be expected during daytime working hours to allow for
truck traffic entering and leaving the cleanup site.

Phase III (Anticipated to begin at the end of the year)
As the project continues with confirmation soil sampling (Appendix E), East Taggart
Street will continue to be open to traffic in both directions all day, with intermittent
traffic stoppages. This is anticipated to continue through the first quarter of 2024, when
the project is currently expected to be completed.


For questions, comments, or concerns, please contact the EPA Information Line at 330-775-
6517.

Latest News Updates


We’re Here to Help

All Latest News Updates

See below for recent updates from East Palestine.

  • Norfolk Southern CEO Awards Second Annual Bulldog Legacy Scholarships to East Palestine High School Seniors 

    Last Updated on May 20, 2024 at 5:25pm Celebrating the extraordinary accomplishments of East Palestine High School’s (EPHS) 2024 graduating class, Norfolk Southern President and CEO Alan H. Shaw announced the four recipients of the Bulldog Legacy Scholarship during a special ceremony Friday, May 17. “Today, we celebrate four exceptional East Palestine High School scholars…

    Read More »

  • Norfolk Southern restores, donates historic East Palestine Train Depot

    Last Updated on May 20, 2024 at 10:13am Village awarded an additional $100,000 grant to transition space into final community use Following a complete restoration of the historic East Palestine train depot, Norfolk Southern officially donated the structure back to the village on May 16. “We promised to rehabilitate the facility and turn it over…

    Read More »

  • NS Field Office officially opens in East Palestine

    Last Updated on April 30, 2024 at 10:24am The Morning Journal published a story about the official opening of Norfolk Southern’s Field Office in East Palestine.  “In the weeks that followed last year’s train derailment in East Palestine, Norfolk Southern CEO Alan Shaw made a promise to the village and surrounding communities. Admittedly, he couldn’t undo…

    Read More »