Home » East Palestine City Park Updates

Check Out Our Work

Our Plans & Progress

Phase 1: Nearing Completion

✓ Installation of new pickleball and sand volleyball courts
✓ Relocation and renovation of the tennis and basketball courts
✓ Additional parking around the dog park
✓ Lighting and sidewalks
• Improvements to the field areas, including grading the oval infield for youth soccer
• Construction of a raised amphitheater near the new sport courts

Phase 2: In Progress

• Creation of state-of-the-art swimming facilities, including an Olympic-size pool area
• Construction of a pool house and driveway
• Demolition of existing sport courts

Phase 3: Planned for the Future

• Reconstructing the playground
• Renovating the brick pavilion
• Enhancing the parking lot construction
• And more*

* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.

Some images are renderings for illustrative purposes and may not be exact replicas of the final product.

Weekly Project Updates

Updated: April 17, 2026

Highlights & Significant Information:

  • Phase 1 is complete: Grass reestablishment is being monitored, with reseeding as needed.
  • Phase 2 is ongoing: Construction continues on the pool house buildout.
  • Phase 3 plans are 100% complete: Norfolk Southern held a pre-bid meeting. Bids have been received and are under review by the project team.
  • The park exit will be closed through April 17 to connect the sanitary sewer main.

Week in Review 4/9/26 to 4/15/26:

  • Phase 2 – Completed interior electrical rough-in
  • Phase 2 – Completed insulating pool house ceiling
  • Phase 2 – Continued work on finish masonry punch list items
  • Phase 2 – Continued installing light pole bases
  • Phase 2 – Continued installing pool tile
  • Phase 2 – Continued final grading for pool deck
  • Phase 2 – Continued installing pool house roofing
  • Phase 2 – Continued installing splash pad features
  • Phase 2 – Started installing drywall ceiling in the pool house
  • Phase 2 – Connected sanitary sewer piping to sewer main
  • Phase 2 – Installed new electrical service to the facility

30-Day Look-Ahead:

  • Phase 2 – Continue installing pool house roofing
  • Phase 2 – Complete stormwater pipe and structures
  • Phase 2 – Complete application of interior wall coatings
  • Phase 2 – Finish grading pool deck area
  • Phase 2 – Install drywall
  • Phase 2 – Paint drywall
  • Phase 2 – Install windows
  • Phase 2 – Install exterior masonry coating
  • Phase 2 – Install fascia and soffit
  • Phase 2 – Install restroom accessories
  • Phase 2 – Pour concrete pool deck

Project Updates Archive

Questions?

For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.

We’re Here to Help

If you have questions or need support, please reach out anytime:

Helpful links for more information and resources: