Home » East Palestine City Park Updates

Check Out Our Work

Our Plans & Progress

Phase 1: Nearing Completion

✓ Installation of new pickleball and sand volleyball courts
✓ Relocation and renovation of the tennis and basketball courts
✓ Additional parking around the dog park
✓ Lighting and sidewalks
• Improvements to the field areas, including grading the oval infield for youth soccer
• Construction of a raised amphitheater near the new sport courts

Phase 2: In Progress

• Creation of state-of-the-art swimming facilities, including an Olympic-size pool area
• Construction of a pool house and driveway
• Demolition of existing sport courts

Phase 3: Planned for the Future

• Reconstructing the playground
• Renovating the brick pavilion
• Enhancing the parking lot construction
• And more*

* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.

Some images are renderings for illustrative purposes and may not be exact replicas of the final product.

Weekly Project Updates

Updated: April 24, 2026

Highlights & Significant Information:

  • Phase 1 is complete: Grass reestablishment is being monitored, with reseeding as needed.
  • Phase 2 is ongoing: Construction continues on the pool house buildout.
  • Phase 3 plans are 100% complete: Norfolk Southern held a pre-bid meeting. Bids have been received and are under review by the project team.

Week in Review 4/16/26 to 4/22/26:

  • Phase 2 – Completed installing light pole bases
  • Phase 2 – Completed final grading for pool deck
  • Phase 2 – Continued work on finish masonry punch list items
  • Phase 2 – Continued installing pool tile
  • Phase 2 – Continued installing pool house roofing
  • Phase 2 – Continued installing splash pad features
  • Phase 2 – Continued installing drywall ceiling in pool house
  • Phase 2 – Started installing light poles
  • Phase 2 – Started pouring concrete for the pool deck
  • Phase 2 – Started installing pool house fascia and soffit
  • Phase 2 – Started preparing pool house flooring installation

30-Day Look-Ahead:

  • Phase 2 – Complete installation of pool house roofing
  • Phase 2 – Complete stormwater pipe and structures
  • Phase 2 – Complete application of interior wall coatings
  • Phase 2 – Install drywall
  • Phase 2 – Paint drywall
  • Phase 2 – Install windows and sills
  • Phase 2 – Install exterior masonry coating
  • Phase 2 – Install fascia and soffit
  • Phase 2 – Install restroom accessories
  • Phase 2 – Pour pool deck concrete
  • Phase 2 – Install pool fence

Project Updates Archive

Questions?

For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.