East Palestine City Park Updates

Updated: November 3, 2025

Norfolk Southern is partnering with the Village of East Palestine for a $25-million renovation of the East Palestine City Park, investing in the park’s future as a social hub for the local residents and an attraction for regional community gatherings, sporting events, fireworks and more. Designed to preserve the park’s history and natural beauty, the project includes essential upgrades and aesthetic improvements and will be completed over several phases.

Phase 2 Currently Underway

Project Timeline

Current Phase

Phase 1 includes the installation of new pickleball and sand volleyball courts, relocation and renovation of the tennis and basketball courts, improvements to the field areas, including grading the oval infield for youth soccer, additional parking around the dog park, lighting, sidewalks, and constructing a raised amphitheater near the new sport courts.

Target completion: Spring 2025

Next Steps

Phase 2 plans for the state-of-the-art swimming facilities include an Olympic-size pool area and pool house, as well as demolition of existing sport courts and construction of new pool house driveway.

Target completion: Summer 2026

Phase 3: Playground reconstruction, brick pavilion renovations, enhanced parking lot construction, and more.*

* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.

Some images are renderings for illustrative purposes and may not be exact replicas of the final product.

Project Updates

Week in Review 10/23 to 10/29:

  • Phase 2 – Grouted foundation walls of pool house
  • Phase 2 – Installed underslab plumbing inside pool house
  • Phase 2 – Installed underslab electrical inside pool house
  • Phase 2 – Continued installing sanitary sewer piping and structures
  • Phase 2 – Formed and poured equipment pit walls inside pool house
  • Phase 2 – Installed waterproofing on pool house foundation walls

30-Day Look-Ahead:

  • Phase 1 – Complete punch list items
  • Phase 2 – Continue installing sanitary sewer piping and structures
  • Phase 2 – Continue installing stormwater pipe and structures
  • Phase 2 – Place shotcrete for pool floor and walls – estimated start 11/3
  • Phase 2 – Install pool gutter
  • Phase 2 – Install gas line
  • Phase 2 – Construct structural masonry walls of pool house

Highlights/Significant Information:

  • Park closure planned during work hours the week of 11/3 due to increased construction traffic for shotcrete work.
  • Main exit closure planned in the coming weeks for sewer and gas line installation.
  • 60% plans for phase 3: Norfolk Southern and Michael Baker International are working to implement Village feedback and comments into phase 3 plans.

Questions?

For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.