Updates on the East Palestine City Park
Norfolk Southern is investing in the future of the Village of East Palestine’s park as a social hub for residents and an attraction for regional community gatherings. We are partnering with the Village for a $25-million renovation, designed to preserve the park’s history and natural beauty. The project includes essential upgrades and aesthetic improvements and will be completed over several phases.
Check Out Our Work
Our Plans & Progress
Phase 1: Nearing Completion
✓ Installation of new pickleball and sand volleyball courts
✓ Relocation and renovation of the tennis and basketball courts
✓ Additional parking around the dog park
✓ Lighting and sidewalks
• Improvements to the field areas, including grading the oval infield for youth soccer
• Construction of a raised amphitheater near the new sport courts
Phase 2: In Progress
• Creation of state-of-the-art swimming facilities, including an Olympic-size pool area
• Construction of a pool house and driveway
• Demolition of existing sport courts
Phase 3: Planned for the Future
• Reconstructing the playground
• Renovating the brick pavilion
• Enhancing the parking lot construction
• And more*
* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.



Some images are renderings for illustrative purposes and may not be exact replicas of the final product.
Weekly Project Updates
Highlights & Significant Information:
- Phase 1 is complete: Grass reestablishment is being monitored, with reseeding as needed.
- Phase 2 is ongoing: Construction continues on the pool house buildout.
- Phase 3 plans are 100% complete: Norfolk Southern held a pre-bid meeting, and bids are due mid-March.
Week in Review 2/26/26 to 3/4/26:
- Phase 2 – Continued plumbing for pool equipment inside the pool house
- Phase 2 – Continued installing pool pumps and equipment inside the pool house
- Phase 2 – Continued HVAC rough-in for pool house
- Phase 2 – Continued interior wall coatings
- Phase 2 – Continued internal coatings for pool tanks
- Phase 2 – Continued installing rigid insulation on exterior walls
- Phase 2 – Continued installing finish masonry on exterior walls
- Phase 2 – Continued installing stormwater pipe and structures
30-Day Look-Ahead:
- Phase 2 – Install pool house roofing
- Phase 2 – Continue interior electrical rough-in
- Phase 2 – FirstEnergy to set new electrical service pole
- Phase 2 – Connect sanitary sewer piping to sewer main
- Phase 2 – Complete stormwater pipe and structures
- Phase 2 – Complete plumbing for pool equipment inside the pool house
- Phase 2 – Complete interior masonry walls of pool house
- Phase 2 – Complete interior wall coatings
- Phase 2 – Finish grading pool deck area
Project Updates Archive
Questions?
For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.
