East Palestine City Park Updates
Norfolk Southern is partnering with the Village of East Palestine for a $25-million renovation of the East Palestine City Park, investing in the park’s future as a social hub for the local residents and an attraction for regional community gatherings, sporting events, fireworks and more. Designed to preserve the park’s history and natural beauty, the project includes essential upgrades and aesthetic improvements and will be completed over several phases.
Phase 2 Currently Underway








Project Timeline
Current Phase
Phase 1 includes the installation of new pickleball and sand volleyball courts, relocation and renovation of the tennis and basketball courts, improvements to the field areas, including grading the oval infield for youth soccer, additional parking around the dog park, lighting, sidewalks, and constructing a raised amphitheater near the new sport courts.
Target completion: Spring 2025
Next Steps
Phase 2 plans for the state-of-the-art swimming facilities include an Olympic-size pool area and pool house, as well as demolition of existing sport courts and construction of new pool house driveway.
Target completion: Summer 2026
Phase 3: Playground reconstruction, brick pavilion renovations, enhanced parking lot construction, and more.*
* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.



Some images are renderings for illustrative purposes and may not be exact replicas of the final product.
Project Updates
East Palestine Park Weekly Updates
Week in Review 7/10 to 7/16:
- Phase 1 – Completed two of three concrete pours of sidewalk around stage
- Phase 1 – Started basketball coatings
- Phase 1 – Reseeded infield area
- Phase 1 – Held walkthrough with Village personnel
- Phase 2 – Installed water tap
- Phase 2 – Installed stormwater basins and piping
30-Day Look-Ahead:
- Phase 1 – Complete basketball court coatings
- Phase 1 – Basketball court equipment installation
- Phase 1 – Pavement striping at dog park parking area
- Phase 1 – Complete stage – pour final sidewalk connections, install railings
- Phase 1 – Install baffles in stormwater basin when weather allows and basin is dry
- Phase 2 – Install sanitary sewer piping and structures
- Phase 2 – Install surge tanks for pool
Highlights/Significant Information:
- Authorized contractor to proceed with demolition work; work to follow completion of necessary abatement which is scheduled to start early August.
Questions?
For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.