Home » East Palestine City Park Updates

East Palestine City Park Updates

Updated: May 29, 2025

Norfolk Southern is partnering with the Village of East Palestine for a $25-million renovation of the East Palestine City Park, investing in the park’s future as a social hub for the local residents and an attraction for regional community gatherings, sporting events, fireworks and more. Designed to preserve the park’s history and natural beauty, the project includes essential upgrades and aesthetic improvements and will be completed over several phases.

Footage as of: Sept. 2024

Project Timeline

Current Phase

Phase 1 includes the installation of new pickleball and sand volleyball courts, relocation and renovation of the tennis and basketball courts, improvements to the field areas, including grading the oval infield for youth soccer, additional parking around the dog park, lighting, sidewalks, and constructing a raised amphitheater near the new sport courts.

Target completion: Spring 2025

Next Steps

Phase 2 plans for the state-of-the-art swimming facilities include an Olympic-size pool area and pool house, as well as demolition of existing sport courts and construction of new pool house driveway.

Target completion: Summer 2026

Phase 3: Playground reconstruction, brick pavilion renovations, enhanced parking lot construction, and more.*

* Construction is ongoing, and plans are subject to change. We are working closely with Village leadership on all decisions.

Some images are renderings for illustrative purposes and may not be exact replicas of the final product.

Project Updates

Week in Review 5/22 to 5/28:

  • Continued landscaping – some rework required – target completion by 5/30
  • Started court fencing
  • Installed surface paving at dog park parking area

30-Day Look-Ahead:

  • Complete sport court fencing – target 5/30/25
  • Court equipment and coating – target start 6/2/25 (delayed due to weather)
  • Pavement striping at dog park parking area – pending weather
  • Install stage wall panels – target start 6/2
  • Pour stage cap – preparing & forming started 5/28
  • Install stage railings – following concrete pour
  • Fill in gaps in sidewalks, connections to stage and courts
  • Complete electrical service connection – pending Ohio Edison crew availability
  • Seeding planned for 5/29/25 – pending weather
  • Install baffles in stormwater basin – pending weather

Highlights/Significant Information:

  • Target substantial completion for Phase 1 construction pushed back to early June due to weather delays.
    • Final stage completion will extend beyond this date due to material lead times for the wall panels. Material is currently scheduled to be onsite by 5/30/25 which will push back completion of the stage area to July.
  • Permits received from ODOH on 4/10-4/11 for all three pool features.
    • Phase 2 can begin as scheduled.
  • Phase 2 contract finalized between NS Sourcing and Kinley Construction.
    • Kinley confirmed start date of 6/16/25.

Questions?

For questions about progress on renovations in the park, please contact the Norfolk Southern Family Assistance Center at 330-426-8400 during operating hours.